SILENT PARK CONSTRUCTION PROGRESS - AUGUST 2023[:] - LEV Development (Лев Девелопмент)

SILENT PARK CONSTRUCTION PROGRESS – AUGUST 2023

August 2023
25

In August 2023:

House 1:

  • Masonry of interior partitions on the 2nd and 3rd floors continued;
  • Work continued on the insulation of the facade;
  • The construction of communications for heating and water supply continued on the 4th and 5th floors.

House 2:

  • Internal walls and partitions of 2-4 floors were carried out;
  • The roof was insulated and screeds were installed on it.

House 3:

  • Concrete works have been completed;
  • Masonry of the external walls of the 1st floor was carried out.

House 4:

  • The concreting of the vertical structures of the 1st residential floor has been completed;
  • The installation of the floor slab above the 1st residential floor has been completed;
  • Vertical structures of the 2nd residential floor were being installed.

Parking:

  • Concreting of half of the foundations has been completed;
  • Work has begun on the installation of concrete walls and columns.
/