In August 2023:
House 1:
- Masonry of interior partitions on the 2nd and 3rd floors continued;
- Work continued on the insulation of the facade;
- The construction of communications for heating and water supply continued on the 4th and 5th floors.
House 2:
- Internal walls and partitions of 2-4 floors were carried out;
- The roof was insulated and screeds were installed on it.
House 3:
- Concrete works have been completed;
- Masonry of the external walls of the 1st floor was carried out.
House 4:
- The concreting of the vertical structures of the 1st residential floor has been completed;
- The installation of the floor slab above the 1st residential floor has been completed;
- Vertical structures of the 2nd residential floor were being installed.
Parking:
- Concreting of half of the foundations has been completed;
- Work has begun on the installation of concrete walls and columns.