As of August 2024:
- Section IV:
- 50% of the brickwork of the walls and partitions of the parking lots has been completed.
- Section V:
- 50% of the brickwork of the walls and partitions of the parking lots has been completed;
- Windows and balcony doors on the 3rd floor are being installed.
- Section VI:
- 70% of the brickwork of the walls and partitions of the parking lots has been completed;
- Installation of batteries and installation of heating system pipes is 40% completed;
- The power supply installation is fully completed;
- Work is underway to insulate the facades.