PERFECT LIFE CONSTRUCTION PROGRESS - August 2024[:] - LEV Development (Лев Девелопмент)

PERFECT LIFE CONSTRUCTION PROGRESS – August 2024

August 2024
22

As of August 2024:

  • In the I section:
    • Corridors and staircases of floors 2-7 are being painted;
    • Work on the improvement of the surrounding area is being carried out;
    • Mailboxes are installed.

 

  • In the II section:
    • Work on the improvement of the surrounding area is being carried out;
    • Mailboxes are installed.

 

  • In the III section:
    • Corridors and staircases of floors 2-5 are being painted;
    • Railings on balconies are being installed;
    • Mailboxes are installed.

 

  • In the IV section:
    • Work has begun on painting the corridors and staircase;
    • Mounted mailboxes.

 

  • In the V section:
    • Droppers have been installed on the balconies;
    • Metal parapets have been installed;
    • Entrance doors in entrances 1 and 2 have been installed;
    • Plastering works are being carried out in the 2nd entrance.

 

  • In the VI section:
    • 80% of the work on the facade has been completed;
    • Low-current networks (Internet) are being laid.

 

  • In Section VII:
    • Masonry of the walls and partitions of the 4th floor has been completed;
    • The external walls of the 5th and 6th floors were bricked;
    • Ventilation ducts are installed;
    • We are building internal walls and partitions of the 5th floor;
    • Window structures have been installed on the 1st-3rd floors;
    • Work on the arrangement of the facade has begun.

 

  • In Section VIII:
    • Masonry of the walls and partitions of the 4th floor has been completed;
    • Ventilation ducts are installed;
    • We are building the walls and partitions of the 5th floor.

 

  • In Section IX:
    • Low-current networks (Internet) were carried out;
    • A semi-dry cement-sand screed was poured in the MZK and apartments on the 5th-7th floors;
    • The installation of the screed on the 4th floor is in progress;
    • Facade work is 70% completed.
/