As of August 2024:
- In the I section:
- Corridors and staircases of floors 2-7 are being painted;
- Work on the improvement of the surrounding area is being carried out;
- Mailboxes are installed.
- In the II section:
- Work on the improvement of the surrounding area is being carried out;
- Mailboxes are installed.
- In the III section:
- Corridors and staircases of floors 2-5 are being painted;
- Railings on balconies are being installed;
- Mailboxes are installed.
- In the IV section:
- Work has begun on painting the corridors and staircase;
- Mounted mailboxes.
- In the V section:
- Droppers have been installed on the balconies;
- Metal parapets have been installed;
- Entrance doors in entrances 1 and 2 have been installed;
- Plastering works are being carried out in the 2nd entrance.
- In the VI section:
- 80% of the work on the facade has been completed;
- Low-current networks (Internet) are being laid.
- In Section VII:
- Masonry of the walls and partitions of the 4th floor has been completed;
- The external walls of the 5th and 6th floors were bricked;
- Ventilation ducts are installed;
- We are building internal walls and partitions of the 5th floor;
- Window structures have been installed on the 1st-3rd floors;
- Work on the arrangement of the facade has begun.
- In Section VIII:
- Masonry of the walls and partitions of the 4th floor has been completed;
- Ventilation ducts are installed;
- We are building the walls and partitions of the 5th floor.
- In Section IX:
- Low-current networks (Internet) were carried out;
- A semi-dry cement-sand screed was poured in the MZK and apartments on the 5th-7th floors;
- The installation of the screed on the 4th floor is in progress;
- Facade work is 70% completed.