As of August 2024:
House 1:
- Works on laying tiles on the terraces are being carried out;
- Installation of entrance doors to apartments has begun.
House 2:
- Finished painting the halls;
- The installation of the balcony fencing has been completed;
- The tiles on the terraces are 100% laid.
House 3:
- Plastering works have started;
- 100% of the work on laying tiles in the halls, 80% on the terraces has been started;
- The internal gasification of the house has been completed by 30%;
- Landscaping between 1-2 houses is 100% finished, works on land-scaping between 2-3 houses have started.
House 4:
- Finished the installation of monolithic walls and columns -2 level of the stylobate between the 3rd and 4th building;
- The installation of the water supply system for heating on the 1st floor has been completed.
House 5:
- Finished plastering works;
- Facade works are being carried out;
- The concrete slab above the -1 level of the parking lot between the 5th and 6th buildings was concreted;
- The installation of the drainage system has been completed.
House 6:
- The installation of window structures on the 1st, 2nd and 3rd floors has been completed;
- The installation of the collective smoke removal system and the ventilation system was completed;
- We are building interior partitions on the 4th and 5th floors.