SILENT PARK CONSTRUCTION PROGRESS - August 2024[:] - LEV Development (Лев Девелопмент)

SILENT PARK CONSTRUCTION PROGRESS – August 2024

August 2024
20

As of August 2024:

House 1:

  • Works on laying tiles on the terraces are being carried out;
  • Installation of entrance doors to apartments has begun.

 

House 2:

  • Finished painting the halls;
  • The installation of the balcony fencing has been completed;
  • The tiles on the terraces are 100% laid.

 

House 3:

  • Plastering works have started;
  • 100% of the work on laying tiles in the halls, 80% on the terraces has been started;
  • The internal gasification of the house has been completed by 30%;
  • Landscaping between 1-2 houses is 100% finished, works on land-scaping between 2-3 houses have started.

 

House 4:

  • Finished the installation of monolithic walls and columns -2 level of the stylobate between the 3rd and 4th building;
  • The installation of the water supply system for heating on the 1st floor has been completed.

 

House 5:

  • Finished plastering works;
  • Facade works are being carried out;
  • The concrete slab above the -1 level of the parking lot between the 5th and 6th buildings was concreted;
  • The installation of the drainage system has been completed.

 

House 6:

  • The installation of window structures on the 1st, 2nd and 3rd floors has been completed;
  • The installation of the collective smoke removal system and the ventilation system was completed;
  • We are building interior partitions on the 4th and 5th floors.
/