Хід будівництва ЖК HYGGE - Construction progress of HYGGE - - Ноябрь 2020[:] - LEV Development

Construction progress of HYGGE – November 2020

November 2020
30

In November 2020:

  • Completed the laying of interior walls in -1 parking lot;
  • Completed plumbing work in the 2nd section and continues in commerce and underground parking;
  • Facade works continued in sections 2 and 3, completed in section 1;
  • Completed the installation of electricity in the 3rd section;
  • Landscaping of about 1-2 sections continued;
  • Completed waterproofing of terraces;
  • Continued plastering of interior walls in the 3rd section;
  • Installation of balcony railings in the 1st section was completed and started in the 2nd section;
  • Finished laying tiles on the balconies of the 1st section;
  • Window ebbs were installed in the 2nd section.
Residential Complex
Number of rooms
1 2 3 4 5 6 7
Square, m2
Price, UAH / m2
Floor
More options
SELECT APARTMENT
запис на консультацію