In November 2020:
- Completed the laying of interior walls in -1 parking lot;
- Completed plumbing work in the 2nd section and continues in commerce and underground parking;
- Facade works continued in sections 2 and 3, completed in section 1;
- Completed the installation of electricity in the 3rd section;
- Landscaping of about 1-2 sections continued;
- Completed waterproofing of terraces;
- Continued plastering of interior walls in the 3rd section;
- Installation of balcony railings in the 1st section was completed and started in the 2nd section;
- Finished laying tiles on the balconies of the 1st section;
- Window ebbs were installed in the 2nd section.