Construction progress of OBRIY 3 - November 2020 - LEV Development

Construction progress of OBRIY 3 – November 2020

November 2020
30

In November 2020:

  • Concrete works on arrangement of arrival in -2 and -1 parking of 2, 3, 4 sections are begun;
  • The masonry of walls and partitions in the 1st section has been completed;
  • 70% of the walls and partitions of the 2nd, 3rd and 4th sections of the 1st floor were laid;
  • 15% of walls and partitions of 2, 3, 4 sections of the 2nd floor were made;
  • Concreting of walls and columns of the 4th residential floor of 2, 3, 4 sections is completed;
  • Concreting of the floor slab above the 4th floor has been completed;
  • Concreting of walls and columns of the 5th residential floor of 2, 3, 4 sections is completed;
  • 30% of the floor slab is arranged above the 5th floor.
запис на консультацію