In November 2020:
- Concrete works on arrangement of arrival in -2 and -1 parking of 2, 3, 4 sections are begun;
- The masonry of walls and partitions in the 1st section has been completed;
- 70% of the walls and partitions of the 2nd, 3rd and 4th sections of the 1st floor were laid;
- 15% of walls and partitions of 2, 3, 4 sections of the 2nd floor were made;
- Concreting of walls and columns of the 4th residential floor of 2, 3, 4 sections is completed;
- Concreting of the floor slab above the 4th floor has been completed;
- Concreting of walls and columns of the 5th residential floor of 2, 3, 4 sections is completed;
- 30% of the floor slab is arranged above the 5th floor.