Хід будівництва ЖК HYGGE - Construction progress of HYGGE - - Сентябрь 2020[:] - LEV Development

Construction progress of HYGGE – September 2020

October 2020
08

In September 2020:

  • Facade works in the 1st and 2nd sections continued;
  • Performed laying of internal walls on -1, -2 levels of parking;
  • Work on plumbing continued in the 2nd section;
  • The installation of electricity on the 1st-6th floor of the 2nd section continued;
  • Completed the installation of external sewerage;
  • Carried out preparatory work for landscaping near the 1st section;
  • Arranged evasive screeds on the insert 1-2.