In September 2020:
- The masonry of the external walls of the 10th and technical floors has been completed;
- 80% of the interior walls and partitions on the 8th, 9th and 10th floors have been laid;
- The roof waterproofing of the 1st section is arranged;
- Concreted walls of commerce 3, 4 sections;
- Concrete slab over the commerce 3, 4 sections;
- Concreted walls and columns of 1 residential floor 2, 3, 4 sections;
- Concrete slab over the 2nd, 3rd, 4th floor.