Construction progress of HYGGE – October 2020

November 2020
04

In October 2020:

  • We continued laying the interior walls at -1 level of the parking lot and have already completed the laying at -2 level; 4
  • Installed plumbing in the 2nd section, commerce and parking;
  • Facade works continued in the 2nd and 3rd sections, completed in the 1st section;
  • Electricity was installed in the 2nd section on 1-6 floors;
  • Arranged landscaping near the 1st section, inserts 1-2;
  • Arranged sloping screeds of terraces on the insert 2-3;
  • Performed waterproofing of terraces on insert 1-2, section 1 (6th floor);
  • Plastered the inner walls of the 3rd section (1-4 floors);
  • Performed waterproofing of the roof in the 2nd section.