Construction progress of OBRIY 3 - October 2020 - LEV

Construction progress of OBRIY 3 – October 2020

November 2020
05

In October 2020:

  • The masonry of the inner walls and partitions of the 8th and 9th floors of the 1st section has been completed;
  • Concreted walls and columns of the 2nd residential floor 2-4 sections;
  • Concrete slab over the 2nd floor of 2-4 sections;
  • Arranged walls and columns of the 3rd residential floor of 2-4 sections;
  • Concrete slab over the 3rd floor of 2-4 sections;
  • Bricklaying of walls and partitions of the 1st residential floor of 2-4 sections has started.