In March 2021:
- Installation of window constructions in the 1st section has begun;
- Facade works on the 1st section have begun;
- The masonry of the walls and partitions of the 4th floor has been completed;
- 40% of masonry walls and partitions of 5-6 floors were made;
- The masonry of the parapets in the 2nd section has been completed;
- The system of collective smoke removal in the 1st section and on 50% in 2-4 sections is mounted;
- 50% of sewer risers are installed in 2-4 sections.