Construction progress of OBRIY 3 - - Март 2021[:] - LEV Development

Construction progress of OBRIY 3 – March 2021

April 2021
02

In March 2021:

  • Installation of window constructions in the 1st section has begun;
  • Facade works on the 1st section have begun;
  • The masonry of the walls and partitions of the 4th floor has been completed;
  • 40% of masonry walls and partitions of 5-6 floors were made;
  • The masonry of the parapets in the 2nd section has been completed;
  • The system of collective smoke removal in the 1st section and on 50% in 2-4 sections is mounted;
  • 50% of sewer risers are installed in 2-4 sections.
Residential Complex
Number of rooms
1 2 3 4 5 6 7
Square, m2
Price, UAH / m2
Floor
More options
SELECT APARTMENT
запис на консультацію