Construction progress of OBRIY 3 - January 2021 - LEV Development

Construction progress of OBRIY 3 – January 2021

February 2021
01

In January 2021:

  • completed the laying of parapets of sections 2, 3 and 4;
  • 80% arranged ventilation ducts;
  • 30% of the walls and partitions of the 4th floor were laid;
  • 40% performed the masonry of the outer walls of 5, 6 floors;
  • started work on the entrance to the 2nd level of the parking lot.