In January 2021:
- completed the laying of parapets of sections 2, 3 and 4;
- 80% arranged ventilation ducts;
- 30% of the walls and partitions of the 4th floor were laid;
- 40% performed the masonry of the outer walls of 5, 6 floors;
- started work on the entrance to the 2nd level of the parking lot.