As of March 2025:
Section I:
- Work is underway on the parking lot’s fire extinguishing system.
- Navigation (numbering) of floors in the entrance has been installed.
Sections II, III, IV:
- Navigation (numbering) of floors in the entrances has been installed.
- The concrete industrial floor in the parking lot has been partially completed.
- The courtyard is being landscaped: trees and shrubs are being planted, and the installation of a rolled lawn has begun.
Section V:
- Work is underway to improve the courtyard area.
- Boilers have been installed in the apartments.
Section VI:
- Preparatory work is being carried out for the improvement of the courtyard area.
VII-VIII sections:
- Installation of elevators has begun.
Section IX:
- Work is underway to improve the courtyard.
Plastering work is being carried out.
General works:
- External sewer networks are being laid from sections VI, VII, VIII, IX.