SILENT PARK CONSTRUCTION PROGRESS - March 2025[:] - LEV Development (Лев Девелопмент)

SILENT PARK CONSTRUCTION PROGRESS – March 2025

March 2025
25

As of March 2025:

Buildings 1-3:

  • The installation of the glass fence of the terraces of the third building has been completed.
  • The installation of decorative wooden panels has been completed.
  • Work is underway to install industrial parking floors.

Buildings 4-5:

  • Intercoms have been installed.
  • Tile installation has begun at the MZK.
  • Planting of green spaces on the stylobates has begun.

House 6:

  • The installation of screeds in apartments and MZK has begun.
  • Installation of balcony railings has begun.
  • Facade work is 80% complete.
  • Installation of the water supply and heating system in the 2nd entrance has begun.

Additional works:

  • The installation of aluminum structures for commercial premises continues.
  • Work has begun on installing a fire protection system on the -2nd level of the parking lot.
  • The parking garage gates are 50% installed.
/