In June 2023:
- In the I section:
- Installation of windows is 90% complete;
- Masonry of partitions on the 3rd, 4th, 6th, 7th, 8th floors has been completed;
- Masonry of partitions on 2.5 floors continued;
- The laying of pipes for the heating and water supply system continued on the 6th, 7th, and 8th floors.
- In the II and III sections:
- Monolithic works are 100% completed;
- Masonry of walls and partitions continued on the 2nd, 3rd, and 7th floors;
- Assembled ventilation ducts on floors 2-5.
- In the IV section:
- Monolithic works are completed by 95%;
- Masonry of the walls on the 1st floor continued.
- In the V section:
- Concrete walls and parking columns were installed.
- In the VI section:
- They arranged a slab for the foundation;
- Concrete walls and parking columns were installed.