PERFECT LIFE CONSTRUCTION PROGRESS - JUNE 2023[:] - LEV Development (Лев Девелопмент)

PERFECT LIFE CONSTRUCTION PROGRESS – JUNE 2023

July 2023
07

In June 2023:

  • In the I section:
    • Installation of windows is 90% complete;
    • Masonry of partitions on the 3rd, 4th, 6th, 7th, 8th floors has been completed;
    • Masonry of partitions on 2.5 floors continued;
    • The laying of pipes for the heating and water supply system continued on the 6th, 7th, and 8th floors.

 

  • In the II and III sections:
    • Monolithic works are 100% completed;
    • Masonry of walls and partitions continued on the 2nd, 3rd, and 7th floors;
    • Assembled ventilation ducts on floors 2-5.

 

  • In the IV section:
    • Monolithic works are completed by 95%;
    • Masonry of the walls on the 1st floor continued.

 

  • In the V section:
    • Concrete walls and parking columns were installed.

 

  • In the VI section:
    • They arranged a slab for the foundation;
    • Concrete walls and parking columns were installed.
/