In June 2023:
House 1:
- The masonry of the 1st, 4th, and 5th floors has been completed;
- Masonry of interior partitions on the 2nd and 3rd floors has begun;
- Windows and balcony blocks have been installed;
- A tilt-forming screed and waterproofing of the roof are arranged;
- Work has begun on the insulation of the facade.
House 2:
- Masonry of external walls is finished;
- Masonry of internal walls has begun;
- Ventilation systems are 90% installed;
- Measurements of window systems were carried out.
House 3:
- Finished concrete works on the installation: floor slabs of the 2nd floor; walls and columns of the 3rd floor; floor slabs of the 3rd floor; walls and columns of the 4th floor.
House 4:
- The foundation slab and walls and columns of the 2nd floor are concreted.