SILENT PARK CONSTRUCTION PROGRESS - JUNE 2023[:] - LEV Development (Лев Девелопмент)

SILENT PARK CONSTRUCTION PROGRESS – JUNE 2023

July 2023
07

In June 2023:

House 1:

  • The masonry of the 1st, 4th, and 5th floors has been completed;
  • Masonry of interior partitions on the 2nd and 3rd floors has begun;
  • Windows and balcony blocks have been installed;
  • A tilt-forming screed and waterproofing of the roof are arranged;
  • Work has begun on the insulation of the facade.

House 2:

  • Masonry of external walls is finished;
  • Masonry of internal walls has begun;
  • Ventilation systems are 90% installed;
  • Measurements of window systems were carried out.

House 3:

  • Finished concrete works on the installation: floor slabs of the 2nd floor; walls and columns of the 3rd floor; floor slabs of the 3rd floor; walls and columns of the 4th floor.

House 4:

  • The foundation slab and walls and columns of the 2nd floor are concreted.
/