PERFECT LIFE CONSTRUCTION PROGRESS - APRIL 2023[:] - LEV Development (Лев Девелопмент)

PERFECT LIFE CONSTRUCTION PROGRESS – APRIL 2023

April 2024
22

As of April 2024:

  • In the I section:
    • Facade work continues;
    • The railings on the balconies are 100% installed;
    • Work has begun on the plastering of the corridors on the floors.

 

  • In the II section:
    • Facade works are being carried out;
    • Work has begun on the plastering of the corridors on the floors.

 

  • In the III section:
    • Facade works are being carried out;
    • Gas pipes are being laid along the facade of the house.

 

  • In the IV section:
    • Facade works are being carried out;
    • Ceramic tiles in the corridors and staircase are 100% complete.

 

  • In the V section:
    • The installation of screeds in the apartments has been completed;
    • Construction of the facade is in progress.

 

  • In the VI section:
    • Masonry is completed;
    • We install sewer risers;
    • Installation of the roof (insulation and evasive screed) has begun.

 

  • In Section VII:
    • The PM above the 2nd floor, the vertical elements of the 2nd floor, and the PM above the 3rd floor are concreted;
    • The 1st floor is bricked;
    • We are concreting the vertical elements of the 4th floor.

 

  • In Section VIII:
    • The PM above the 2nd floor, the vertical elements of the 2nd floor, and the PM above the 3rd floor are concreted;
    • The 1st floor is bricked;
    • We are building the 2nd floor;
    • We are concreting the vertical elements of the 4th floor.

 

  • In Section IX:
    • Window structures have been installed (except for the 1st floor and staircase);
    • The 1st layer of the roof is made;
    • We install plumbing networks (water, heating).
/