As of April 2024:
- In the I section:
- Facade work continues;
- The railings on the balconies are 100% installed;
- Work has begun on the plastering of the corridors on the floors.
- In the II section:
- Facade works are being carried out;
- Work has begun on the plastering of the corridors on the floors.
- In the III section:
- Facade works are being carried out;
- Gas pipes are being laid along the facade of the house.
- In the IV section:
- Facade works are being carried out;
- Ceramic tiles in the corridors and staircase are 100% complete.
- In the V section:
- The installation of screeds in the apartments has been completed;
- Construction of the facade is in progress.
- In the VI section:
- Masonry is completed;
- We install sewer risers;
- Installation of the roof (insulation and evasive screed) has begun.
- In Section VII:
- The PM above the 2nd floor, the vertical elements of the 2nd floor, and the PM above the 3rd floor are concreted;
- The 1st floor is bricked;
- We are concreting the vertical elements of the 4th floor.
- In Section VIII:
- The PM above the 2nd floor, the vertical elements of the 2nd floor, and the PM above the 3rd floor are concreted;
- The 1st floor is bricked;
- We are building the 2nd floor;
- We are concreting the vertical elements of the 4th floor.
- In Section IX:
- Window structures have been installed (except for the 1st floor and staircase);
- The 1st layer of the roof is made;
- We install plumbing networks (water, heating).