SILENT PARK CONSTRUCTION PROGRESS – APRIL 2023

April 2024
22

As of April 2024:

House 1:

  • Painting works are underway.

House 2:

  • Tile work in the entrances is 95% completed;
  • Ebbs and parapet covers are 100% completed.

House 3:

  • Heating and water supply have been completed;
  • 100% screeds are poured;
  • Work on the installation of drippers and parapet covers has been completed;
  • Installation of insulation and PVC membrane between the first and second houses has been completed;
  • Improvement works have started;
  • Preparatory work is underway to install insulation and a PVC membrane between the second and third houses.

House 4:

  • The plastering works of the 1st entrance are being completed;
  • The arrangement of the screed on the roof is completed;
  • Facade works are being carried out;
  • Work has begun on the installation of sewer risers.

House 5:

  • Installation of window structures has begun;
  • Masonry of walls on 2-3 floors has been completed;
  • 50% of the masonry of the walls and partitions of the 1st, 4th, and 5th floors has been completed;
  • The installation of the collective smoke removal system and the ventilation system has been completed.

House 6:

  • The concreting of the vertical structures of the 2nd floor has been completed.
/