As of April 2024:
House 1:
- Painting works are underway.
House 2:
- Tile work in the entrances is 95% completed;
- Ebbs and parapet covers are 100% completed.
House 3:
- Heating and water supply have been completed;
- 100% screeds are poured;
- Work on the installation of drippers and parapet covers has been completed;
- Installation of insulation and PVC membrane between the first and second houses has been completed;
- Improvement works have started;
- Preparatory work is underway to install insulation and a PVC membrane between the second and third houses.
House 4:
- The plastering works of the 1st entrance are being completed;
- The arrangement of the screed on the roof is completed;
- Facade works are being carried out;
- Work has begun on the installation of sewer risers.
House 5:
- Installation of window structures has begun;
- Masonry of walls on 2-3 floors has been completed;
- 50% of the masonry of the walls and partitions of the 1st, 4th, and 5th floors has been completed;
- The installation of the collective smoke removal system and the ventilation system has been completed.
House 6:
- The concreting of the vertical structures of the 2nd floor has been completed.