Construction progress of the PERFECT LIFE – April 2026 - LEV Development (Лев Девелопмент)

Construction progress of the PERFECT LIFE – April 2026

April 2026
23

As of April 2026 :

Section V:

  • Landscaping work is underway;
  • Marking has begun in the parking lot;
  • The elevator hall door in the parking lot has been installed.

Section VI:

  • Lighting fixtures are being installed on the 1st and 5th floors.

Section VII:

  • Walls were puttied;
  • Entrance doors to the apartments have been installed.

Section VIII:

  • Tile laying continues;
  • Entrance doors to apartments have been installed;
  • Painting work is underway.

Section IX:

  • Tile laying continues;
  • Entrance doors to apartments have been installed;
  • Painting work is underway.
/