As of April 2026 :
Section 1:
- The installation of windows and doors on the facade has been completed.
- Work is underway to install waterproofing on terraces.
- Work is underway to insulate the facade of the building.
- We are continuing work on laying heating and water supply networks on the 3rd-4th floors.
- Work on the installation of apartment power supply systems has been completed
Section 2:
- Preparatory work has begun for waterproofing the roof of the house.
- Work on the brickwork of the walls and partitions of the 6th and 1st floors has been completed.
- Monolithic work has begun on the arrangement of the silobat part of the house.
Section 3:
- Work on the installation of vertical reinforced concrete roof structures has been completed.
- Work is underway to install brickwork on the walls and partitions of the 1st and 2nd floors.
- Installation of window structures in the house has begun.
Section 4:
- Installation of window structures in the house has begun.
- We are completing the work on installing the brickwork of the walls and partitions of the 1st floor.
- We continue work on laying heating and water supply networks
Section 5:
- We are completing work on installing facade insulation.
- Plastering work has begun in the entrance.
- Work has begun on installing brickwork in commercial premises.
Section B8:
- Work is underway to install the floor slab on the 4th floor.
Section B7:
- Work on the construction of vertical reinforced concrete structures of walls and columns of the 3rd floor has been completed.
- Work on the installation of the 3rd floor floor slab has been completed.
- Work is underway to install vertical reinforced concrete structures of walls and columns on the 4th floor.
Section B6:
- Work is underway to install vertical reinforced concrete structures of walls and columns on the 1st floor.
Section B5:
- Work on the construction of vertical reinforced concrete structures of walls and columns of the 2nd floor has been completed.
- Work is underway to install the floor slab on the 2nd floor.
Section B4:
- Work on the construction of vertical reinforced concrete structures of walls and columns of the 1st floor has been completed.
- Work is underway to install the floor slab on the 1st floor.
Section B3:
- Work on the installation of the 1st floor floor slab has been completed.
- Work is underway to install vertical reinforced concrete structures of walls and columns on the 2nd floor.
Section B2:
- Work on the installation of the floor slab on the 1st floor of the parking lot has been completed.
- Work is underway to install vertical reinforced concrete structures of walls and columns on the 2nd floor.
Section B1:
- Work on the installation of the floor slab on the 1st floor of the parking lot has been completed.
- Work is underway to install vertical reinforced concrete structures of walls and columns on the 1st floor.