Construction progress of Soul Park – April 2026 - LEV Development (Лев Девелопмент)

Construction progress of Soul Park – April 2026

April 2026
22

As of April 2026  :

Section 1:

  • The installation of windows and doors on the facade has been completed.
  • Work is underway to install waterproofing on terraces.
  • Work is underway to insulate the facade of the building.
  • We are continuing work on laying heating and water supply networks on the 3rd-4th floors.
  • Work on the installation of apartment power supply systems has been completed

Section 2:

  • Preparatory work has begun for waterproofing the roof of the house.
  • Work on the brickwork of the walls and partitions of the 6th and 1st floors has been completed.
  • Monolithic work has begun on the arrangement of the silobat part of the house.

Section 3:

  • Work on the installation of vertical reinforced concrete roof structures has been completed.
  • Work is underway to install brickwork on the walls and partitions of the 1st and 2nd floors.
  • Installation of window structures in the house has begun.

Section 4:

  • Installation of window structures in the house has begun.
  • We are completing the work on installing the brickwork of the walls and partitions of the 1st floor.
  • We continue work on laying heating and water supply networks

Section 5:

  • We are completing work on installing facade insulation.
  • Plastering work has begun in the entrance.
  • Work has begun on installing brickwork in commercial premises.

Section B8:

  • Work is underway to install the floor slab on the 4th floor.

Section B7:

  • Work on the construction of vertical reinforced concrete structures of walls and columns of the 3rd floor has been completed.
  • Work on the installation of the 3rd floor floor slab has been completed.
  • Work is underway to install vertical reinforced concrete structures of walls and columns on the 4th floor.

Section B6:

  • Work is underway to install vertical reinforced concrete structures of walls and columns on the 1st floor.

Section B5:

  • Work on the construction of vertical reinforced concrete structures of walls and columns of the 2nd floor has been completed.
  • Work is underway to install the floor slab on the 2nd floor.

Section B4:

  • Work on the construction of vertical reinforced concrete structures of walls and columns of the 1st floor has been completed.
  • Work is underway to install the floor slab on the 1st floor.

Section B3:

  • Work on the installation of the 1st floor floor slab has been completed.
  • Work is underway to install vertical reinforced concrete structures of walls and columns on the 2nd floor.

Section B2:

  • Work on the installation of the floor slab on the 1st floor of the parking lot has been completed.
  • Work is underway to install vertical reinforced concrete structures of walls and columns on the 2nd floor.

Section B1:

  • Work on the installation of the floor slab on the 1st floor of the parking lot has been completed.
  • Work is underway to install vertical reinforced concrete structures of walls and columns on the 1st floor.
/