As of February 2026 :
Section V:
- Power cabinets have been installed in the electrical switchboard room;
- Installation of the ventilation system in the parking lot is underway;
- MDF linings are being installed above apartment doors.
Section VI:
- Power cables have been laid to the electricity metering cabinets.
Section VII:
- Electricity metering cabinets have been installed on the floors;
- Power cables have been laid to the electricity metering cabinets.
Section VIII:
- Painting work is underway at the MZK (preparing walls for puttying);
- Power cables have been laid to the electricity metering cabinets.
Section IX:
- Power cabinets have been installed in the electrical switchboard room;
- The installation of MDF linings above the apartment doors has been completed;
- Installation of the ventilation system in the parking lot is underway.