Construction progress of the PERFECT LIFE – February 2026 - LEV Development (Лев Девелопмент)

Construction progress of the PERFECT LIFE – February 2026

February 2026
26

As of February 2026  :

Section V:

  • Power cabinets have been installed in the electrical switchboard room;
  • Installation of the ventilation system in the parking lot is underway;
  • MDF linings are being installed above apartment doors.

Section VI:

  • Power cables have been laid to the electricity metering cabinets.

Section VII:

  • Electricity metering cabinets have been installed on the floors;
  • Power cables have been laid to the electricity metering cabinets.

Section VIII:

  • Painting work is underway at the MZK (preparing walls for puttying);
  • Power cables have been laid to the electricity metering cabinets.

Section IX:

  • Power cabinets have been installed in the electrical switchboard room;
  • The installation of MDF linings above the apartment doors has been completed;
  • Installation of the ventilation system in the parking lot is underway.
/