Construction progress of the VERO – February 2026

February 2026
26

As of February 2026:

  • Section A3: Reinforces the foundation slab;
  • Section A4: The concrete base for the foundation slab is 100% complete;
  • Section A5: Carrying out excavation work;
  • Section A6: We are developing a foundation pit.
/