PERFECT LIFE CONSTRUCTION PROGRESS - MAY 2023[:] - LEV Development (Лев Девелопмент)

PERFECT LIFE CONSTRUCTION PROGRESS – MAY 2023

May 2024
23

As of May 2024:

  • In the I section:
    • Corridors and staircases of floors 2-7 are being plastered;
    • Electricity metering cabinets are installed in the corridors.

 

  • In the II section:
    • Corridors and staircases of floors 2-5 are being plastered;
    • Sprinklers are being installed on the balconies.

 

  • In the III section:
    • Facade works are being carried out;
    • Gas pipes are being laid in apartments.

 

  • In the IV section:
    • Facade works are being carried out;
    • Gas pipes are being laid in apartments.

 

  • In the V section:
    • Construction of the facade is in progress;
    • Plastering works are in progress;

 

  • In the VI section:
    • Installation of window structures is in progress;
    • The installation of sewer risers has been completed;
    • An evasive screed on the roof was made.

 

  • In Section VII:
    • The vertical elements of the 4th floor and the floor slab above the 4th floor are concreted;
    • The brickwork of the 2nd floor is in progress;
    • We are concreting the vertical elements of the 5th floor.

 

  • In Section VIII:
    • The vertical elements of the 4th floor and the floor slab above the 4th floor are concreted;
    • The brickwork of the 2nd floor is in progress;
    • We are concreting the vertical elements of the 5th floor.

 

  • In Section IX:
    • Construction of the facade is in progress;
    • Installation of plumbing networks is in progress;
    • The balconies are waterproofed.
/
Residential Complex
Number of rooms
1 2 3 4 5 6 7
Square, m2
Price, UAH / m2
Floor
More options
SELECT APARTMENT