As of May 2024:
- In the I section:
- Corridors and staircases of floors 2-7 are being plastered;
- Electricity metering cabinets are installed in the corridors.
- In the II section:
- Corridors and staircases of floors 2-5 are being plastered;
- Sprinklers are being installed on the balconies.
- In the III section:
- Facade works are being carried out;
- Gas pipes are being laid in apartments.
- In the IV section:
- Facade works are being carried out;
- Gas pipes are being laid in apartments.
- In the V section:
- Construction of the facade is in progress;
- Plastering works are in progress;
- In the VI section:
- Installation of window structures is in progress;
- The installation of sewer risers has been completed;
- An evasive screed on the roof was made.
- In Section VII:
- The vertical elements of the 4th floor and the floor slab above the 4th floor are concreted;
- The brickwork of the 2nd floor is in progress;
- We are concreting the vertical elements of the 5th floor.
- In Section VIII:
- The vertical elements of the 4th floor and the floor slab above the 4th floor are concreted;
- The brickwork of the 2nd floor is in progress;
- We are concreting the vertical elements of the 5th floor.
- In Section IX:
- Construction of the facade is in progress;
- Installation of plumbing networks is in progress;
- The balconies are waterproofed.