SILENT PARK CONSTRUCTION PROGRESS – MAY 2023

May 2024
23

As of May 2024:

House 1:

  • Painting works are completed by 60%;
  • Automatic lawn watering and street lighting networks are being laid around the first house and between the first and second houses.

House 2:

  • Tile work in the entrances is 100% completed.

House 3:

  • Water metering cabinets have been installed.

House 4:

  • The plastering work of the 2nd entrance has begun;
  • The installation of sewer risers has been completed;
  • Facade works are underway.

House 5:

  • We build cells in the parking lot;
  • We are building the 4th and 5th floors.

House 6:

  • The slab above the 2nd floor is concreted.
/