As of May 2024:
House 1:
- Painting works are completed by 60%;
- Automatic lawn watering and street lighting networks are being laid around the first house and between the first and second houses.
House 2:
- Tile work in the entrances is 100% completed.
House 3:
- Water metering cabinets have been installed.
House 4:
- The plastering work of the 2nd entrance has begun;
- The installation of sewer risers has been completed;
- Facade works are underway.
House 5:
- We build cells in the parking lot;
- We are building the 4th and 5th floors.
House 6:
- The slab above the 2nd floor is concreted.