As of May 2026 :
Section V:
- Painting and markings in the parking lot have been completed.
- Landscaping is underway
- We install a smoke removal system from the parking lot
Section VI:
- Landscaping is underway
- Gas boilers installed in apartments
Section VII:
- Tile laying continues
- Gas boilers installed in apartments
- Landscaping is underway
Section VIII:
- Tile installation completed
- Gas boilers installed in apartments
- Painting work is 70% complete
Section IX:
- Painting and markings in the parking lot have been completed.
- We install a smoke removal system from the parking lot