As of May 2026  :

Section V:

  • Painting and markings in the parking lot have been completed.
  • Landscaping is underway
  • We install a smoke removal system from the parking lot

Section VI:

  • Landscaping is underway
  • Gas boilers installed in apartments

Section VII:

  • Tile laying continues
  • Gas boilers installed in apartments
  • Landscaping is underway

Section VIII:

  • Tile installation completed
  • Gas boilers installed in apartments
  • Painting work is 70% complete

Section IX:

  • Painting and markings in the parking lot have been completed.
  • We install a smoke removal system from the parking lot
/