Construction progress of Soul Park – May 2026 - LEV Development (Лев Девелопмент)

Construction progress of Soul Park – May 2026

May 2026
25

As of May 2026:

Section 1:

  • Work is underway to install waterproofing on terraces.
  • Work is underway to insulate the facade of the building.
  • Work has begun on laying electrical networks.
  • We continue work on waterproofing balconies.
  • Work has begun on landscaping the territory
  • Work has begun on installing a ventilated facade.
  • Plastering work has begun in the entrance of the house.

Section 2:

  • We are completing the plastering work in the entrance of the house.
  • Work has begun on laying water supply and heating networks.
  • We are completing monolithic work on the arrangement of the silobat part of the house.
  • The installation of window structures in the house has been completed.

Section 3:

  • We are completing the work on installing the brickwork of the walls and partitions on the 2nd floor.
  • We continue to install window structures in the house.

Section 4:

  • Plastering work has begun in the entrance of the house
  • We continue work on insulating facades.

Section 5:

  • Work has begun on installing balcony railings
  • Work has begun on installing semi-dry screed in the apartments and entrance.
  • Work has begun on the parapet roofing.

Section B8:

  • Work on the construction of vertical reinforced concrete structures of walls and columns of the 5th floor has been completed.
  • Work is underway to install the floor slab on the 5th floor.
  • Work is underway to install brickwork on the walls and partitions of the 1st floor.

Section B7:

  • Work is underway to install vertical reinforced concrete structures of walls and columns on the 4th floor.

Section B6:

  • Work on the construction of vertical reinforced concrete structures of walls and columns of the 1st floor has been completed.
  • Work on the installation of the 1st floor floor slab has been completed.
  • Work on the construction of vertical reinforced concrete structures of walls and columns of the 2nd floor has been completed.
  • Work is underway to install the floor slab on the 2nd floor.

Section B5:

  • Work on the construction of vertical reinforced concrete structures of walls and columns of the 3rd floor has been completed.
  • Work is underway to install the 3rd floor slab.

Section B4:

  • Work is underway to install vertical reinforced concrete structures of walls and columns on the 1st floor of the parking lot.

Section B3:

  • Work on the construction of vertical reinforced concrete structures of walls and columns of the 2nd floor (residential building) has been completed.
  • Work on the installation of the floor slab of the 2nd floor of the stylobate parking lot has been completed.
  • Work is underway to install the floor slab on the 1st floor of the stylobate parking lot.

Section B2:

  • Work on the construction of vertical reinforced concrete structures of walls and columns of the 1st floor of a residential building has been completed.
  • Work is underway to install the floor slab on the 1st floor.

Section B1:

  • Work is underway to install the floor slab on the 1st floor.
/