As of September 2024:
- In the I section:
- Works on the improvement of the territory of the house are being carried out.
- In the II section:
- Corridors and staircases of floors 2-6 are being painted.
- In the III section:
- Corridors and staircases of floors 2-5 are being painted.
- In the IV section:
- Corridors and staircases of floors 2-5 are being painted;
- Work on the installation of railings on the balconies is underway.
- In the V section:
- Plastering works are being carried out in the 2nd entrance;
- Installed apartment doors in the 1st entrance;
- Laying of ceramic tiles in the MZK of the 1st entrance is in progress;
- Painting work (plastering of corridors) of the 1st entrance has begun.
- In the VI section:
- Installation of electrical networks (installation of input cables to apartments) is in progress.
- In Section VII:
- Masonry of internal walls and partitions of the 5th floor has been completed;
- We are building internal walls and partitions of the 6th floor;
- Installation of shingles has begun;
- Warming and pouring of the roof screed is in progress;
- Construction of the facade is in progress.
- In Section VIII:
- Masonry of the walls and partitions of the 5th floor has been completed;
- We are building internal walls and partitions of the 6th floor.
- In Section IX:
- Work is underway to arrange the facade;
- The installation of the screed in the apartments and MZK has been completed.