PERFECT LIFE CONSTRUCTION PROGRESS - September 2024[:] - LEV Development (Лев Девелопмент)

PERFECT LIFE CONSTRUCTION PROGRESS – September 2024

September 2024
18

As of September 2024:

  • In the I section:
    • Works on the improvement of the territory of the house are being carried out.

 

  • In the II section:
    • Corridors and staircases of floors 2-6 are being painted.

 

  • In the III section:
    • Corridors and staircases of floors 2-5 are being painted.

 

  • In the IV section:
    • Corridors and staircases of floors 2-5 are being painted;
    • Work on the installation of railings on the balconies is underway.

 

  • In the V section:
    • Plastering works are being carried out in the 2nd entrance;
    • Installed apartment doors in the 1st entrance;
    • Laying of ceramic tiles in the MZK of the 1st entrance is in progress;
    • Painting work (plastering of corridors) of the 1st entrance has begun.

 

  • In the VI section:
    • Installation of electrical networks (installation of input cables to apartments) is in progress.

 

  • In Section VII:
    • Masonry of internal walls and partitions of the 5th floor has been completed;
    • We are building internal walls and partitions of the 6th floor;
    • Installation of shingles has begun;
    • Warming and pouring of the roof screed is in progress;
    • Construction of the facade is in progress.

 

  • In Section VIII:
    • Masonry of the walls and partitions of the 5th floor has been completed;
    • We are building internal walls and partitions of the 6th floor.

 

  • In Section IX:
    • Work is underway to arrange the facade;
    • The installation of the screed in the apartments and MZK has been completed.
/
Residential Complex
Number of rooms
1 2 3 4 5 6 7
Square, m2
Price, UAH / m2
Floor
More options
SELECT APARTMENT