As of September 2024:
Building 1:
- Terrace tiles have been laid by 80%;
- Entrance doors to the apartments have been installed;
- Work on the gasification of the building has begun;
- Balcony waterproofing has been completed.
Building 2:
- Entrance doors to the apartments have been installed;
- Balcony waterproofing work is underway;
- The internal gasification of the building is 35% complete.
Building 3:
- Plastering work in the entrances has been completed;
- Terrace tiles have been laid by 100%;
- Entrance doors to the apartments have been installed;
- Landscaping between buildings 2 and 3 is 70% complete;
- Landscaping work has begun on the southern and eastern parts of the territory;
- Work is being carried out on glazing and ventilated facades of commercial premises.
Building 4:
- Concrete flooring on level -1 of the parking between sections 3 and 4 has been completed;
- The installation of vertical elements on level -1 of the parking has been completed;
- Screed installation on the 1st floor of section 4 has been completed;
- Installation of PVC membrane on the stylobate between sections 4 and 5 has begun.
Building 5:
- Heating system installation work is being carried out on the 5th, 4th, and 3rd floors of entrance 1;
- Installation of the second layer of roofing felt on the roof has begun;
- Facade work is 80% complete.
Building 6:
- Wall and partition masonry work in the building has been completed;
- The installation of slope screeds on the roof has begun;
- Storage cell masonry in the parking area is ongoing;
- Monolithic work on the stylobate part near section 6 is underway.