SILENT PARK CONSTRUCTION PROGRESS - September 2024[:] - LEV Development (Лев Девелопмент)

SILENT PARK CONSTRUCTION PROGRESS – September 2024

September 2024
23

As of September 2024:

Building 1:

  • Terrace tiles have been laid by 80%;
  • Entrance doors to the apartments have been installed;
  • Work on the gasification of the building has begun;
  • Balcony waterproofing has been completed.

Building 2:

  • Entrance doors to the apartments have been installed;
  • Balcony waterproofing work is underway;
  • The internal gasification of the building is 35% complete.

Building 3:

  • Plastering work in the entrances has been completed;
  • Terrace tiles have been laid by 100%;
  • Entrance doors to the apartments have been installed;
  • Landscaping between buildings 2 and 3 is 70% complete;
  • Landscaping work has begun on the southern and eastern parts of the territory;
  • Work is being carried out on glazing and ventilated facades of commercial premises.

Building 4:

  • Concrete flooring on level -1 of the parking between sections 3 and 4 has been completed;
  • The installation of vertical elements on level -1 of the parking has been completed;
  • Screed installation on the 1st floor of section 4 has been completed;
  • Installation of PVC membrane on the stylobate between sections 4 and 5 has begun.

Building 5:

  • Heating system installation work is being carried out on the 5th, 4th, and 3rd floors of entrance 1;
  • Installation of the second layer of roofing felt on the roof has begun;
  • Facade work is 80% complete.

Building 6:

  • Wall and partition masonry work in the building has been completed;
  • The installation of slope screeds on the roof has begun;
  • Storage cell masonry in the parking area is ongoing;
  • Monolithic work on the stylobate part near section 6 is underway.
/