As of October 2024:
Section 1:
- Painting of the corridors and staircase is 95% complete;
- Work has begun on the installation of gas boilers.
Section 2:
- Painting of the corridors and staircase is 90% completed;
- Work is being carried out on the arrangement of the adjoining territory (inner yard).
Section 3:
- Painting of the corridors and staircase is 90% completed;
- Work is being carried out on the arrangement of the adjoining territory (inner yard).
Section 4:
- Painting of the corridors and staircase is 90% completed;
- Work is being carried out on the arrangement of the adjoining territory (inner yard).
Section 5:
- Plastering works have been completed;
- Laying of ceramic tiles in the MZK of the 1st entrance is 80% completed;
- Painting works are ongoing in the 1st entrance;
- Installation of gas risers is in progress;
- Preparatory work for the installation of balcony fences is being carried out.
Section 6:
- The laying of electrical cables along the MZK has been completed;
- Hanging of radiators and installation of plumbing networks is carried out;
- Plastering works have started.
Section 7:
- Masonry of walls and partitions on the 6th floor has been completed;
- The insulation and the evasive screed on the roof have been performed;
- 1 layer of roofing material is mounted;
- Construction of the facade is in progress.
Section 8:
- Masonry of walls and partitions on the 6th floor has been completed;
- Masonry of walls and partitions on the 7th floor is in progress;
- The insulation and the evasive screed on the roof have been completed.
Section 9:
- Preparatory work for the installation of balcony fences is in progress;
- Drippers have been installed on the balconies.