SILENT PARK CONSTRUCTION PROGRESS - October 2024[:] - LEV Development (Лев Девелопмент)

SILENT PARK CONSTRUCTION PROGRESS – October 2024

October 2024
25

As of October 2024:

House 1:

  • Aluminum doors were installed on the 5th floor;
  • The gasification of the house is 100% completed;
  • Installation of the glass enclosure on the terraces of the 5th floor is 80% complete.

House 2:

  • Work on the waterproofing of the balconies has been completed;
  • Aluminum doors were installed on the 5th floor;
  • Gasification is 70% complete.

House 3:

  • The painting of entrances has been completed;
  • Aluminum doors were installed on the 5th floor;
  • Installation of double-glazed windows of stylobate windows is 70% completed;
  • Land improvement works are underway.

House 4:

  • Installation of the PVC membrane on the stylobate between 3 and 4 houses has begun;
  • Partitions are being installed in the shelter and transformer substation;
  • Tile installation on the terraces has been completed;
  • Installation of tiles in the MZK of the 1st entrance has begun.

House 5:

  • Installation of the heating and water supply system has been completed;
  • Work has begun on the installation of the stylobate foundations between the 5th and 6th buildings;
  • Facade work is 95% completed.

House 6:

  • Plastering work in the 1st entrance has been completed;
  • Installation of waterproofing on the roof has been completed;
  • Facade work has begun;
  • Masonry of cells in parking lots is being done.
/