As of October 2024:
House 1:
- Aluminum doors were installed on the 5th floor;
- The gasification of the house is 100% completed;
- Installation of the glass enclosure on the terraces of the 5th floor is 80% complete.
House 2:
- Work on the waterproofing of the balconies has been completed;
- Aluminum doors were installed on the 5th floor;
- Gasification is 70% complete.
House 3:
- The painting of entrances has been completed;
- Aluminum doors were installed on the 5th floor;
- Installation of double-glazed windows of stylobate windows is 70% completed;
- Land improvement works are underway.
House 4:
- Installation of the PVC membrane on the stylobate between 3 and 4 houses has begun;
- Partitions are being installed in the shelter and transformer substation;
- Tile installation on the terraces has been completed;
- Installation of tiles in the MZK of the 1st entrance has begun.
House 5:
- Installation of the heating and water supply system has been completed;
- Work has begun on the installation of the stylobate foundations between the 5th and 6th buildings;
- Facade work is 95% completed.
House 6:
- Plastering work in the 1st entrance has been completed;
- Installation of waterproofing on the roof has been completed;
- Facade work has begun;
- Masonry of cells in parking lots is being done.