PERFECT LIFE CONSTRUCTION PROGRESS – October 2025

October 2025
20

As of October 2025 :

Section V:

  • Side trims are mounted on the door;
  • We are installing a facade in the parking lot exit area.

Section VI:

  • Side panels are installed on the door.

Section VII:

  • Preparatory work has begun before plastering the entrance.

Section VIII:

  • Plastering work is 60% complete;
  • Installation of balcony railings is underway;
  • Waterproofing is being carried out on the balconies.

Section IX:

  • The landscaping of the exterior of the entrance has been completed;
  • The facade of the commercial premises has been completed.
/