As of October 2025 :
1 section
- The installation of the 5th floor floor slab has been completed.
- Work on the installation of vertical wall and column structures on the 6th floor has been completed.
- Work on the installation of the 6th floor slab has been completed.
- Work is underway to install vertical monolithic reinforced concrete roof structures.
- Work on the brickwork of the walls and partitions of the 3rd floor has been completed.
- Work on the brickwork of the walls and partitions of the 4th floor has been completed.
- Work is underway to install brickwork on the walls and partitions of the 5th floor.
Section 2
- Work on the installation of vertical wall and column structures on the 5th floor has been completed.
- Work on the installation of the 5th floor floor slab has been completed.
- Work is underway to install vertical wall and column structures on the 5th floor.
- Work is underway to install brickwork on the walls and partitions of the 2nd floor.
Section 3
- Work on the installation of the 1st floor floor slab has been completed.
- Work on the installation of vertical wall and column structures on the 2nd floor has been completed.
- Work on the installation of the 2nd floor floor slab has been completed.
- Work is underway to install vertical wall and column structures on the 3rd floor.
Section 4
- Work on the installation of vertical wall and column structures on the 4th floor has been completed.
- Work is underway to install the floor slab on the 4th floor.
- Work is underway to install brickwork on the walls and partitions of the 2nd floor.
Section 5
- Work on the installation of the 6th floor floor slab has been completed.
- Work is underway to install vertical reinforced concrete roof structures.
- Work on the brickwork of the walls and partitions of the 4th floor has been completed.
- Work is underway to install brickwork on the walls and partitions of the 5th floor.