Construction progress of Soul Park – October 2025 - LEV Development (Лев Девелопмент)

Construction progress of Soul Park – October 2025

October 2025
10

As of October 2025 :

1 section

  • The installation of the 5th floor floor slab has been completed.
  • Work on the installation of vertical wall and column structures on the 6th floor has been completed.
  • Work on the installation of the 6th floor slab has been completed.
  • Work is underway to install vertical monolithic reinforced concrete roof structures.
  • Work on the brickwork of the walls and partitions of the 3rd floor has been completed.
  • Work on the brickwork of the walls and partitions of the 4th floor has been completed.
  • Work is underway to install brickwork on the walls and partitions of the 5th floor.

Section 2

  • Work on the installation of vertical wall and column structures on the 5th floor has been completed.
  • Work on the installation of the 5th floor floor slab has been completed.
  • Work is underway to install vertical wall and column structures on the 5th floor.
  • Work is underway to install brickwork on the walls and partitions of the 2nd floor.

Section 3

  • Work on the installation of the 1st floor floor slab has been completed.
  • Work on the installation of vertical wall and column structures on the 2nd floor has been completed.
  • Work on the installation of the 2nd floor floor slab has been completed.
  • Work is underway to install vertical wall and column structures on the 3rd floor.

Section 4

  • Work on the installation of vertical wall and column structures on the 4th floor has been completed.
  • Work is underway to install the floor slab on the 4th floor.
  • Work is underway to install brickwork on the walls and partitions of the 2nd floor.

Section 5

  • Work on the installation of the 6th floor floor slab has been completed.
  • Work is underway to install vertical reinforced concrete roof structures.
  • Work on the brickwork of the walls and partitions of the 4th floor has been completed.
  • Work is underway to install brickwork on the walls and partitions of the 5th floor.
/