As of March 2026 :
Section 1:
- Work is underway to install windows and doors on the facade;
- The installation of water and sewage risers has been completed;
- Work is underway to install waterproofing on terraces;
- Work has begun on installing facade insulation.
Section 2:
- Work on the brickwork of the walls and partitions of the 5th floor has been completed;
- Work is underway to install brickwork on the walls and partitions of the 6th floor;
- The installation of sewer risers and drainage has been completed.
Section 3:
- Work is underway to install vertical reinforced concrete roof structures;
- Work is underway to install brickwork on the walls and partitions of the 2nd floor;
- Work is underway to install brickwork for the walls and partitions of the 3rd, 4th, and 5th floors.
Section 4:
- Work is underway to install brickwork on the walls and partitions of the 5th floor.
Section 5:
- Work is underway to install insulation for facades;
- Work on the installation of heating and water supply systems has been completed;
- Work on installing the apartment power supply systems has been completed.
Section B8:
- Work on the construction of vertical reinforced concrete structures of walls and columns of the 3rd floor has been completed;
- Work on the installation of the 3rd floor floor slab has been completed;
- Work is underway to install vertical reinforced concrete structures of walls and columns on the 4th floor.
Section B7:
- Work on the installation of the 2nd floor floor slab has been completed;
- Work is underway to install vertical reinforced concrete structures of walls and columns on the 3rd floor.
Section B6:
- Work on the construction of vertical reinforced concrete structures of walls and columns of the 1st floor has been completed;
- Work is underway to install the floor slab on the 1st floor.
Section B5:
- Work on the installation of the parking lot floor slab has been completed;
- Work is underway to install vertical reinforced concrete structures of walls and columns on the 1st floor.
Section B4:
- Work is underway to install the floor slab.
Section B3:
- Work on the installation of the parking lot floor slab has been completed;
- Work is underway to install vertical reinforced concrete structures of walls and columns on the 1st floor.
Section B2:
- Work on the construction of vertical reinforced concrete structures of the parking lot walls and columns has been completed;
- Work on the installation of the parking lot floor slab has been completed;
- Work is underway to install vertical reinforced concrete structures of walls and columns of the 1st floor parking lot.
Section B1:
- Work on the construction of vertical reinforced concrete structures of the parking lot walls and columns has been completed;
- Work on the installation of the parking floor slab on the 2nd floor has been completed;
- Work is underway to install vertical reinforced concrete structures of walls and columns on the 1st floor of the parking lot.