Construction progress of Soul Park – March 2026 - LEV Development (Лев Девелопмент)

Construction progress of Soul Park – March 2026

March 2026
25

As of March 2026 :

Section 1:

  • Work is underway to install windows and doors on the facade;
  • The installation of water and sewage risers has been completed;
  • Work is underway to install waterproofing on terraces;
  • Work has begun on installing facade insulation.

Section 2:

  • Work on the brickwork of the walls and partitions of the 5th floor has been completed;
  • Work is underway to install brickwork on the walls and partitions of the 6th floor;
  • The installation of sewer risers and drainage has been completed.

Section 3:

  • Work is underway to install vertical reinforced concrete roof structures;
  • Work is underway to install brickwork on the walls and partitions of the 2nd floor;
  • Work is underway to install brickwork for the walls and partitions of the 3rd, 4th, and 5th floors.

Section 4:

  • Work is underway to install brickwork on the walls and partitions of the 5th floor.

Section 5:

  • Work is underway to install insulation for facades;
  • Work on the installation of heating and water supply systems has been completed;
  • Work on installing the apartment power supply systems has been completed.

Section B8:

  • Work on the construction of vertical reinforced concrete structures of walls and columns of the 3rd floor has been completed;
  • Work on the installation of the 3rd floor floor slab has been completed;
  • Work is underway to install vertical reinforced concrete structures of walls and columns on the 4th floor.

Section B7:

  • Work on the installation of the 2nd floor floor slab has been completed;
  • Work is underway to install vertical reinforced concrete structures of walls and columns on the 3rd floor.

Section B6:

  • Work on the construction of vertical reinforced concrete structures of walls and columns of the 1st floor has been completed;
  • Work is underway to install the floor slab on the 1st floor.

Section B5:

  • Work on the installation of the parking lot floor slab has been completed;
  • Work is underway to install vertical reinforced concrete structures of walls and columns on the 1st floor.

Section B4:

  • Work is underway to install the floor slab.

Section B3:

  • Work on the installation of the parking lot floor slab has been completed;
  • Work is underway to install vertical reinforced concrete structures of walls and columns on the 1st floor.

Section B2:

  • Work on the construction of vertical reinforced concrete structures of the parking lot walls and columns has been completed;
  • Work on the installation of the parking lot floor slab has been completed;
  • Work is underway to install vertical reinforced concrete structures of walls and columns of the 1st floor parking lot.

Section B1:

  • Work on the construction of vertical reinforced concrete structures of the parking lot walls and columns has been completed;
  • Work on the installation of the parking floor slab on the 2nd floor has been completed;
  • Work is underway to install vertical reinforced concrete structures of walls and columns on the 1st floor of the parking lot.
/