Construction progress of the PERFECT LIFE – March 2026 - LEV Development (Лев Девелопмент)

Construction progress of the PERFECT LIFE – March 2026

March 2026
27

As of March 2026  :

Section VII:

  • The installation of cement-sand screed in the MZK and apartments has been completed;
  • Work is underway to install gas supply networks in apartments.

Section VIII:

  • Painting work is being carried out at the MZK;
  • Work is underway to install gas supply networks in apartments;
  • The water supply network is being laid in commercial premises;
  • Mailboxes have been installed.

Section IX:

  • The water supply network is being laid in commercial premises.
/