As of March 2026:
- We concrete the walls and columns of the parking lot of section A3;
- Reinforcement and concreting of the walls and columns of the parking lot of section A4;
- Digging of the pit of section A5;
- Arrangement of concrete preparation for the foundation slab of section A5;
- Digging a pit for section A6;
- Installation of a concrete base under the foundation slab of section A6.