Construction progress of Soul Park – June 2026 - LEV Development (Лев Девелопмент)

Construction progress of Soul Park – June 2026

June 2026
10

As of June 2026  :

In section 1:

  • Installation of balcony railings has begun;
  • Work continues on installing a ventilated facade on one of the walls of the building;
  • Installation of a semi-dry screed in the apartments and entrance of the building has begun;
  • Work continues on improving the territory.

In section 2:

  • Work on installing a semi-dry screed in the entrance has been completed;
  • Work continues on insulating the facade.

In section 3:

  • Plastering work in the entrance of the house has been completed;
  • Work continues on insulating the facade of the building.

In section 4:

  • Installation of a semi-dry screed in the apartments and entrance of the building has begun;
  • Work continues on installing a ventilated facade on one of the walls of the building.

In section 5:

  • Painting work has begun in the entrance;
  • The waterproofing of the terraces in the house is being completed.

In section B8:

  • Work is underway to install vertical reinforced concrete roof structures;
  • Work is underway to install brickwork on the walls and partitions of the 2nd floor;
  • Work is underway to install brickwork on the walls and partitions of the 3rd floor.

In section B7:

  • Work on the construction of vertical reinforced concrete structures of walls and columns of the 5th floor has been completed;
  • Work is underway to install the floor slab on the 5th floor;
  • Work is underway to install brickwork on the walls and partitions of the 2nd floor.

In section B6:

  • Work on the installation of the 3rd floor floor slab has been completed;
  • Work on the construction of vertical reinforced concrete structures of walls and columns of the 4th floor has been completed;
  • Work is underway to install the floor slab on the 4th floor;
  • Work is underway to install brickwork on the walls and partitions of the 2nd floor.

In section B5:

  • Work on the installation of the 4th floor floor slab has been completed;
  • Work is underway to install vertical reinforced concrete structures of walls and columns on the 5th floor;
  • Work is underway to install brickwork on the walls and partitions of the 1st floor.

In section B4:

  • Work on the installation of the floor slab of the 1st floor has been completed;
  • Work is underway to install vertical reinforced concrete structures of walls and columns on the 1st floor.

In section B3:

  • Work on the construction of vertical reinforced concrete structures of walls and columns of the 2nd floor has been completed;
  • Work is underway to install the floor slab on the 2nd floor.

In section B2:

  • Work on the installation of the 2nd floor floor slab has been completed;
  • Work is underway to install vertical reinforced concrete structures of walls and columns on the 3rd floor.

In section B1:

  • Work on the construction of vertical reinforced concrete structures of walls and columns of the 2nd floor has been completed;
  • Work on the installation of the 2nd floor floor slab has been completed;
  • Work is underway to install vertical reinforced concrete structures of walls and columns on the 3rd floor.
/