As of June 2026:
Section A1:
- The foundation slab has been reinforced.
Section A3:
- The floor slab above the 2nd floor has been concreted;
- Reinforcement of the columns of the 3rd floor has begun.
Section A4:
- Work has begun on reinforcing the floor slab above the 2nd floor.
Section A5:
- Work has begun on the installation of the formwork for the floor slab above the 1st floor.
Section A6:
- The walls and columns of the 1st floor have been concreting.