As of July 2026:
In section 1:
- We are continuing work on installing a ventilated facade on one of the walls of the house.
- We continue work on landscaping the territory.
- We have begun installing entrance doors to apartments.
- We carry out preparatory work for installing porcelain stoneware on terraces
- We install an elevator in the entrance
In section 2:
- We continue work on insulating the facade.
- Work has begun on installing the ventilated facade.
- Painting work has begun in public areas.
In section 3:
- We continue work on insulating the facade of the house.
- Installation of balcony railings has begun.
- We are finishing painting work in public areas.
- Begin installing ceramic tiles on the floor in the entrances.
In section 4:
- Painting work in the entrances has been completed.
- We have begun installing ceramic tiles on the floor in the entrance.
- We are continuing work on installing a ventilated facade on one of the walls of the house.
In section 5:
- Painting work in the entrance has been completed.
- Installation of ceramic tiles on the floor in the entrance hall has begun.
- Installation of elevators in the entrance has begun
In section B8:
- Work is underway to install vertical reinforced concrete roof structures.
- Work on the brickwork of the walls and partitions of the 4th floor has been completed.
- Work is underway to install brickwork on the walls and partitions of the 5th floor.
In section B7:
- Work is underway to install vertical reinforced concrete roof structures.
- Work on the brickwork of the walls and partitions of the 2nd floor has been completed.
- Work is underway to install brickwork on the walls and partitions of the 3rd floor.
In section B6:
- Work is underway to install vertical reinforced concrete roof structures.
- Work on the brickwork of the walls and partitions of the 3rd floor has been completed.
- Work is underway to install brickwork on the walls and partitions of the 4th floor.
In section B5:
- Work on the installation of the 5th floor floor slab has been completed.
- Work is underway to install vertical reinforced concrete structures on the 6th floor.
- Work on the brickwork of the walls and partitions of the 1st floor has been completed.
- Work is underway to install brickwork on the walls and partitions of the 2nd floor.
- Work is underway to install brickwork on the walls and partitions of the 3rd floor.
In section B4:
- Work on the installation of the 1st floor floor slab has been completed.
- Work is underway to install vertical reinforced concrete structures on the 2nd floor.
In section B3:
- Work on the construction of vertical reinforced concrete structures of walls and columns of the 3rd floor has been completed.
- Work on the installation of the 3rd floor floor slab has been completed.
- Work is underway to install vertical reinforced concrete structures of walls and columns on the 4th floor.
In section B2:
- Work on the installation of the 4th floor floor slab has been completed.
- Work is underway to install vertical reinforced concrete structures of walls and columns on the 5th floor.
In section B1:
- Work on the construction of vertical reinforced concrete structures of walls and columns of the 4th floor has been completed.
- Work on the installation of the 4th floor floor slab has been completed.
- Work is underway to install vertical reinforced concrete structures of walls and columns on the 5th floor.