Construction progress of Soul Park – July 2026 - LEV Development (Лев Девелопмент)

Construction progress of Soul Park – July 2026

July 2026
19

As of July 2026:

In section 1:

  • We are continuing work on installing a ventilated facade on one of the walls of the house.
  • We continue work on landscaping the territory.
  • We have begun installing entrance doors to apartments.
  • We carry out preparatory work for installing porcelain stoneware on terraces
  • We install an elevator in the entrance

In section 2:

  • We continue work on insulating the facade.
  • Work has begun on installing the ventilated facade.
  • Painting work has begun in public areas.

In section 3:

  • We continue work on insulating the facade of the house.
  • Installation of balcony railings has begun.
  • We are finishing painting work in public areas.
  • Begin installing ceramic tiles on the floor in the entrances.

In section 4:

  • Painting work in the entrances has been completed.
  • We have begun installing ceramic tiles on the floor in the entrance.
  • We are continuing work on installing a ventilated facade on one of the walls of the house.

In section 5:

  • Painting work in the entrance has been completed.
  • Installation of ceramic tiles on the floor in the entrance hall has begun.
  • Installation of elevators in the entrance has begun

In section B8:

  • Work is underway to install vertical reinforced concrete roof structures.
  • Work on the brickwork of the walls and partitions of the 4th floor has been completed.
  • Work is underway to install brickwork on the walls and partitions of the 5th floor.

In section B7:

  • Work is underway to install vertical reinforced concrete roof structures.
  • Work on the brickwork of the walls and partitions of the 2nd floor has been completed.
  • Work is underway to install brickwork on the walls and partitions of the 3rd floor.

In section B6:

  • Work is underway to install vertical reinforced concrete roof structures.
  • Work on the brickwork of the walls and partitions of the 3rd floor has been completed.
  • Work is underway to install brickwork on the walls and partitions of the 4th floor.

In section B5:

  • Work on the installation of the 5th floor floor slab has been completed.
  • Work is underway to install vertical reinforced concrete structures on the 6th floor.
  • Work on the brickwork of the walls and partitions of the 1st floor has been completed.
  • Work is underway to install brickwork on the walls and partitions of the 2nd floor.
  • Work is underway to install brickwork on the walls and partitions of the 3rd floor.

In section B4:

  • Work on the installation of the 1st floor floor slab has been completed.
  • Work is underway to install vertical reinforced concrete structures on the 2nd floor.

In section B3:

  • Work on the construction of vertical reinforced concrete structures of walls and columns of the 3rd floor has been completed.
  • Work on the installation of the 3rd floor floor slab has been completed.
  • Work is underway to install vertical reinforced concrete structures of walls and columns on the 4th floor.

In section B2:

  • Work on the installation of the 4th floor floor slab has been completed.
  • Work is underway to install vertical reinforced concrete structures of walls and columns on the 5th floor.

In section B1:

  • Work on the construction of vertical reinforced concrete structures of walls and columns of the 4th floor has been completed.
  • Work on the installation of the 4th floor floor slab has been completed.
  • Work is underway to install vertical reinforced concrete structures of walls and columns on the 5th floor.
/