Хід будівництва ЖК VERO - Construction progress of the VERO – July 2026 - LEV Development (Лев Девелопмент)

Construction progress of the VERO – July 2026

July 2026
21

As of July 2026:

Section A1:

  • The vertical structures of the parking lot are completed;
  • Work has begun on installing the floor slab over the parking lot.

Section A2:

  • We continue work on installing parking walls and columns.

Section A3:

  • They installed the columns and walls of the 4th floor;
  • They started to assemble the 5th floor slab;
  • We are building the interior walls and partitions of the 2nd floor.

Section A4:

  • They installed the floor slab on the 4th floor;
  • The columns and walls of the 4th floor are complete;
  • Masonry of the exterior walls of the 1st floor has begun.

Section A5:

  • The concreting of the 2nd floor floor slab has been completed;
  • They are carrying out work on installing walls and columns on the 2nd floor.

Section A6:

  • The walls and columns of the 2nd floor are done;
  • Work is underway to install the 3rd floor slab.

Parking:

  • The vertical elements of the 2nd floor are completed.
/
Residential Complex
Number of rooms
1 2 3 4 5 6 7
Square, m2
Price, UAH / m2
Floor
More options
SELECT APARTMENT