As of July 2026:
Section A1:
- The vertical structures of the parking lot are completed;
- Work has begun on installing the floor slab over the parking lot.
Section A2:
- We continue work on installing parking walls and columns.
Section A3:
- They installed the columns and walls of the 4th floor;
- They started to assemble the 5th floor slab;
- We are building the interior walls and partitions of the 2nd floor.
Section A4:
- They installed the floor slab on the 4th floor;
- The columns and walls of the 4th floor are complete;
- Masonry of the exterior walls of the 1st floor has begun.
Section A5:
- The concreting of the 2nd floor floor slab has been completed;
- They are carrying out work on installing walls and columns on the 2nd floor.
Section A6:
- The walls and columns of the 2nd floor are done;
- Work is underway to install the 3rd floor slab.
Parking:
- The vertical elements of the 2nd floor are completed.