In December 2020:
- Installation of dimensional partitions from gypsum cardboard is begun;
- Installation of sewer risers (drainage from the roof and terraces) has been completed;
- Installation of reinforced concrete bridges over window openings is completed;
- The masonry of partitions from the gas block on -1 and -2 floors has been completed;
- The installation of reinforced concrete bridges over the window openings continued.