In July 2020:
- The floor over the 5th floor has been completed;
- Works on concreting the walls and columns of the 6th floor have been completed;
- The installation of the formwork of the floor slab over the 6th floor has begun;
- Completed work on concreting the vertical elements of the 5th floor;
- Work continued on the arrangement of stairs from the 4th to the 5th floor;
- Began to reinforce the floor slab above the 5th floor;
- Concreting of the floor slab above the 3rd floor has been completed;
- Work continued on concreting the vertical elements of the 4th floor;
- Works on concreting of stairs from the 3rd to the 4th floor have been completed.