Construction progress of LEV CITY HOTEL - - Июль 2020[:] - LEV Development

Construction progress of LEV CITY HOTEL – July 2020

August 2020
05

In July 2020:

  • The floor over the 5th floor has been completed;
  • Works on concreting the walls and columns of the 6th floor have been completed;
  • The installation of the formwork of the floor slab over the 6th floor has begun;
  • Completed work on concreting the vertical elements of the 5th floor;
  • Work continued on the arrangement of stairs from the 4th to the 5th floor;
  • Began to reinforce the floor slab above the 5th floor;
  • Concreting of the floor slab above the 3rd floor has been completed;
  • Work continued on concreting the vertical elements of the 4th floor;
  • Works on concreting of stairs from the 3rd to the 4th floor have been completed.