Construction progress of OBRIY 3 - - Июль 2020[:] - LEV Development

Construction progress of OBRIY 3 – July 2020

August 2020
05

In July 2020:

  • The floor slab is arranged above the technical floor in 1 section;
  • The base plate under 3 section is arranged;
  • Installation of walls and columns on -2 levels of underground parking of 3 sections is completed;
  • Arranged floor slab -1 Rihanna underground parking 3 sections;
  • Arranged walls and columns in – 1 level of underground parking;
  • The floor slab of commerce of 3 sections is arranged;
  • The parapet in 1 section is bricked up;
  • External and internal walls of 6,7,8 floors are arranged;
  • 50% of waterproofing of walls and foundations of sections 2, 3 was performed;
  • Sewer risers of 1-5 floors are arranged;
  • Vent ducts to the 9th floor of 1 section are arranged.
Residential Complex
Number of rooms
1 2 3 4 5 6 7
Square, m2
Price, UAH / m2
Floor
More options
SELECT APARTMENT
запис на консультацію