In July 2020:
- The floor slab is arranged above the technical floor in 1 section;
- The base plate under 3 section is arranged;
- Installation of walls and columns on -2 levels of underground parking of 3 sections is completed;
- Arranged floor slab -1 Rihanna underground parking 3 sections;
- Arranged walls and columns in – 1 level of underground parking;
- The floor slab of commerce of 3 sections is arranged;
- The parapet in 1 section is bricked up;
- External and internal walls of 6,7,8 floors are arranged;
- 50% of waterproofing of walls and foundations of sections 2, 3 was performed;
- Sewer risers of 1-5 floors are arranged;
- Vent ducts to the 9th floor of 1 section are arranged.