Хід будівництва ЖК OBRIY 2 - Construction progress of OBRIY 2 - - Июль 2020[:] - LEV Development

Construction progress of OBRIY 2 – July 2020

August 2020
04

In July 2020:

  • We continue to mount the railings on the balconies;
  • We finished laying tiles on the staircase and corridors in sections 1 and 2, started work in sections 3;
  • We putty the walls of the corridors in 2, 3 sections;
  • We finished laying the roof waterproofing;
  • We continue to work on the improvement of the territory;
  • Finished laying ebb and parapet in 1 and 2 sections;
  • Finished laying tiles on the balconies;
  • We install lightning protection and grounding;
  • Completed the installation of fire doors in 2 sections;
  • We mount entrance doors to apartments in sections 1 and 2.