In July 2020:
- Facade works in the 1st section are begun;
- Laying of internal walls on the 4-5th floor proceeds;
- 95% of the masonry of the outer walls in the 3rd section;
- Installation of the sewer system in the 3rd section is completed;
- The installation of the ventilation system and the collective smoke removal system in the 3rd section has been completed;
- Reinforcement and concreting of vertical structures of commerce near the 3rd section continues;
- Mounted window constructions on insert 2-3;
- The insulation of the facade of the 3rd section is arranged.